OILING THE SQUEAKY WHEEL:

Some Recommendations For Limiting The Risk of Claims By Unpaid Suppliers

By P. Douglas Folk, Esq.

 

       

    Late claims for payment by a subcontractor's suppliers present one of the more aggravating contract administration problems in public construction today. The general contractor who has not protected itself and its bond against this risk may face the unpleasant prospect of paying twice for the goods at issue. Even in the best-managed jobs, a subcontractor's supplier can often slip in with a claim just before the ninety-day deadline expires for making claims against Miller Act-type bonds.

     In many of these cases, the general contractor may question whether the supplier's goods actually reached the project on which the bond claim is asserted. Much to its dismay, however, the general contractor will usually find that denying receipt of the disputed materials on the job site does not defeat the supplier's claim.

        Since the supplier is quite often unable to verify with complete certainty that its materials reached the jobsite, the courts have been somewhat liberal in allowing the supplier's claim against the general contractor's payment bond. The supplier will not be required to prove actual delivery or use of its materials in the project. Rather, it need only show that it had a reasonable, good faith belief that its goods were used on the bonded job.

        Even when the general contractor has some solid evidence that the disputed materials have been diverted by the subcontractor to another project altogether, that will not usually be enough to defeat the supplier's claim. For the supplier in this scenario, ignorance is bliss -- or at least, payment in full.

        How then, does the general contractor avoid this unpleasant pinch and "oil the squeaky wheel"? Several procedures can be used, either singly or in combination, to limit the risk of supplier claims against a payment bond. While each of these procedures imposes its own cost on the project -- whether that cost is an increase in a sub's bid or just an increase in time and paperwork -- they can often reduce substantially the much greater risk and cost of a supplier's claim. My personal favorites include the following:

WB00871_.GIF (426 bytes)    Avoid using subcontractors who have not completed a similar project for you in the past, or ones whose bids seem unreasonably low; experience has shown that these situations often carry a greater than expected risk of loss. Lack of a satisfactory track record or a bid which seems too good to be true are automatically red flags for me. In most of the payment bond cases I have seen, the unhappy general contractor usually makes at least one of the following statements during the course of the litigation:

"This was the first (and last) job that subcontractor has ever done for me."

"I knew that subcontractor's bid looked too low when I accepted it."

"I had problems with this subcontractor on the last job, too."

        For those general contractors who find themselves in these "red flag" situations, I highly recommend using the other "tools" described below.

WB00871_.GIF (426 bytes)    Require performance and payment bonds from subcontractors on key portions of the project, or ones which pose a special risk. While payment bonds add to direct costs and can impact the competitiveness of the general contractor's bid, the benefits of this additional protection can be substantial. First, a subcontractor who can get a bond from a reputable surety probably has a well-run operation and can be counted on to pay its suppliers. Second, the bond's protection may justify the general contractor easing up on retention requirements and allowing other concessions which can be factored back in to a more competitive bid from that subcontractor.

WB00871_.GIF (426 bytes)    Require a complete list of the subcontractor's suppliers at the beginning of the project and independently verify the subcontractor's expected purchases for the project. By tracking its subcontractor's suppliers, the general contractor can monitor payment histories, and arrange joint checks when appropriate. Furthermore, if a subcontractor's key suppliers have been notified in advance (preferably in writing) of the expected scope of that subcontractor's purchases and the expected duration of the bonded project, they may be more diligent in collecting payment from the subcontractor.

WB00871_.GIF (426 bytes)    Joint check agreements are still the cheapest form of protection against suppliers' claims. If the general contractor has not required a bond from its subcontractor, controlling the application of its payments is the next best defense. If the supplier fails to retain enough of each progress payment to cover its receivable, it will be barred from bringing a claim against the general contractor or its payment bond. Likewise, if the general contractor sets a dollar limit on its obligation under the joint check agreement, and sticks to that limit, the supplier will have clear notice of the expected scope of purchases for that project.

WB00871_.GIF (426 bytes)    Conditional lien waivers and releases should be required from the supplier before progress payments are released. The general contractor can foreclose any possibility of a supplier's claim by using a lien waiver and release form which verifies that the supplier, upon receiving a specified payment, releases any and all claims for labor or materials supplied through the date of the payment.

WB00871_.GIF (426 bytes)    If a supplier makes a bond claim, get professional advice immediately in evaluating that claim and formulating a proper response. Even though courts interpret the bond statutes liberally to benefit the suppliers who claim under those bonds, strict compliance with legal notice requirements is still enforced. For example, the performance of warranty work or minor punch list items will not extend the time for giving notice of a bond claim. Also, some bond statutes require notice of the claim by registered mail; others do not.

        There are also many subtle differences between the various state and federal payment bond statutes and the language of the bond forms themselves that can be discerned and used by an experienced construction lawyer. A prompt consultation with legal counsel may often reveal some technical defect in the claim which would allow the general contractor and its surety to avoid the liability altogether.

        Pressure can also be brought to bear on the delinquent subcontractor, its surety, or retention funds to offset or reduce the supplier's claim. Subcontractors and suppliers should also note that many of the strategies discussed in this article will also fulfill their desired goal of obtaining payment for valuable labor and materials used in the project. Oiling the "squeaky wheel" does not have to be a process in which one party benefits at the expense of the other.

_______________________________________________________

    ©    Folk & Associates, P.C. All rights reserved to reproduction in any format or medium.